Macy’s flagship
Macy’s flagship - mezzanine curved glass
Challenge
The curved glass comes from abroad and has 3 months lead time.
All the stainless steel fittings must be precisely welded ahead of time, where they belong.
So that when glass shows up, it fits perfectly on the fittings, and gets installed with no delay.
Solution
Cut metal jigs on the waterjet to replicate the radius of the glass.
Maintain an exact X,Y,Z coordinate system on the field ; do not lose the snapped lines during the 3 months lead time of the glass.
Weld each fittings at the location X, Y and Z that it is supposed to be.
Upgrade of the entrances and of the first floor of this iconic building, including 4 brand new curved staircases to access the renewed mezzanine